Work is under way on the city's 2024 pavement rehabilitation program, which has identified eight residential streets for concrete replacement and repair.
Crews started working in early spring on Treasure Isle Circle and Stoneridge Trail, and will move after that to East Bend Drive.
The other streets set for attention, in tentative order, are Moss Point Road, Commons Oval, Sherwood Drive, Wedgewood Drive and Jonathan Drive (Montclare to Prospect).
Each project will take three to four weeks to complete. Residents will be instructed to park overnight on nearby streets during the construction. Emergency vehicles will have access at all times. Mail delivery and trash pickup will be continued during construction, and school transportation has been notified.
Set in Stone Contracting is the contractor for the projects.